North Shore Pump Station

Henry Foundation Drilling Inc. (HFDI) was contracted to execute the comprehensive design-build shoring scope for the new North Shore pump station, strategically positioned directly underneath the historic Lions Gate Bridge.

12-meter deep
Excavation depth (Phase 1)
1,600m³ in a continuous 8-hour window
Underwater tremie slab
three cranes, three concrete pump trucks
Cranes and pump trucks on tremie pour
less than 100 meters
Distance to ocean
less than 3 meters below the working elevation
Groundwater table
eight (8) specialized access shafts (Shafts 2, 6, 8, and 9)
Access shafts (Phase 2)
2.1-meter
Adjacent water pipeline

Phase 1: North Shore Pump Station (Lions Gate Bridge)

Henry Foundation Drilling Inc. (HFDI) was contracted to execute the comprehensive design-build shoring scope for the new North Shore pump station, strategically positioned directly underneath the historic Lions Gate Bridge.

Collaborating closely with the client, HFDI engineered a highly cost-effective and structurally advanced design consisting of a circular secant pile compression ring adjoining an internally braced secant pile shaft.

Phase 2: Wastewater Conveyance Access Shafts (Shafts 2, 6, 8, and 9)

Following the success of Phase 1, Henry Foundation Drilling Inc. was trusted to design and construct the temporary structural shoring for the new pump station expansion along with eight (8) specialized access shafts.

This critical infrastructure phase facilitates the installation of sub-surface conveyance piping designed to transfer wastewater efficiently from the existing Lions Gate Wastewater Treatment Plant to the state-of-the-art North Shore Wastewater Treatment Plant.